0
Answered

project minimums at project level?

mark 7 years ago in Home Portal / Classic Projects updated by Łukasz Kaleta (Senior Customer Success Manager) 6 years ago 1

I have a question about project minimums and want to make sure we're doing this correctly. 


It seems that project minimums are set in the price profiles and can be set at the Task level or the Task Receivable level. Is this correct? 


So, is there an option to have a project minimum for the full project also? 


We frequently have projects with multiple languages pairs that we need to apply a project minimum to. So, we end up applying a project minimum to one task, then apply a discount of 100% to the second task. It works, but makes the invoice a bit confusing. Is there another way of doing this? Am I missing a function in XTRF?

Answered

It is not possible to have a minimum per project. It is because the biggest financial items in XTRF are tasks. You may think of projects as just collections of tasks.