Planned Start Date and Planned Deadline for a job

Planned Start Date and Planned Deadline set time frames for each of the Jobs. 

They are expressed as date and time, according to the setting chosen in Image 1768 Configuration > General Configuration > Settings > Number and Date Formatting

While it is up to you when exactly to set up the dates, they are both mandatory in order to change the Job's status from Opened to Accepted, or send a Job Offer for it. 

Planned Start Date and Deadline can be set up manually, or by an appropriate Automation, described here.

Setting up the dates

To set the dates manually for a single Job, you can use either of the below methods:

  • Use the Select Dates button directly on the Job and work in the pop-up to define each of the dates.

Select dates in XTRF Projects 01

Select dates in XTRF Projects 02

  • In case you have more than one Job in a Step, use the side panel, which appears when you select a Job. This works just fine in case of a single Job too. 

Select dates in XTRF Projects 03

    • Use the Gantt Chart in the 'Jobs' card just below. You can switch between the list of Jobs and the chart using the cogwheel button. 

    Select dates in XTRF Projects 04

    Now you can drag the Job, as well as its edges on the timeline.

    Image 638

    Note

    In case of multiple Jobs within a Step it is a good idea to first drag the Step over the timeline and then split it.

    Where do you see these dates?

    Both dates are available to the vendor, displayed in the Vendor Portal, respectively as 'Start Date' and 'Deadline'.

    Select dates in XTRF Projects 05

    They can also be seen within a single Job.

    Select dates in XTRF Projects 06

    Moreover, the dates are printed in the standard Purchase Order, but without exact time.

    Image 641

    What do the dates do?

    In general, they establish the ideal timeline of the project's particular steps.

    Note that the project itself might start earlier than the start date of the initial, and end later than the deadline of the terminal Job in the process, providing extra time for project management. 

    Image 642

    If the deadline is exceeded, the Project Manager will receive an appropriate alert, described in this article. The subsequent Job is not automatically 'Started' just because its predecessor is delayed. It will wait until it's actually finished. 

    If the Job is delivered before deadline, the next Job in line will be 'Started' (unless the project process is set up not to start the next Job). 

    If you decide to change the dates while the Job is 'Started', the Vendor will receive an appropriate notification, which is triggered two minutes after the occurrence (to allow further change or correction, if the date was changed by mistake).  

    Is this article helpful for you?