Examples of project deadline settings

Jaime Zuniga 7 years ago updated by Maciej (XTRF Senior Deployment & Training Specialist) 7 years ago 1

HI,


I'm having a problem understanding what values to put in a workflow definition given the following steps in a classic project:


request sending     5%

memoQ prep          5%

translation              60%

editing                    25%

memoQ export       5%


What values would I need to put in the workflow definition if I wanted the above percentages reflected in the project deadlines?

Answer

Answer
Answered

In the time&requests tab you can use these exact values without % sign. They don't need to add up to 100, by the way. 


If the Task start to deadline time is long enough, the jobs duration will be set accordingly.

GOOD, I'M SATISFIED

Thanks!


Jaime

Satisfaction mark by Jaime Zuniga 7 years ago
Answer
Answered

In the time&requests tab you can use these exact values without % sign. They don't need to add up to 100, by the way. 


If the Task start to deadline time is long enough, the jobs duration will be set accordingly.